Most of Malibu is not on a sewer. Homes use onsite wastewater treatment systems, which the city calls OWTS. Because a failing system can harm the creeks, the lagoon and the ocean, the City of Malibu ties septic compliance to the sale of a home. If you buy or sell in Malibu, the septic inspection is one of the first things to plan for.
Key takeaways
Malibu requires an OWTS operating permit when a property is sold if a valid, unexpired permit is not already in place.
The inspection must be done by a City-Registered OWTS Inspector.
If a system fails, the owner signs a notarized compliance agreement within 30 days, and the sale can still close under that agreement.
Buyers must file a change-of-ownership notice within 30 days of closing to transfer an existing permit.
What the rule says
Malibu Municipal Code Chapter 15.44 sets the city's OWTS operating permit program, and the point-of-sale procedure was added in 2008. Permits are required to build or run a new system, and for existing systems a permit must be obtained when:
the property is sold and has no valid, unexpired operating permit,
a septic permit is issued for a repair, or
the property applies for a short-term rental permit.
If the home already has a valid operating permit that isn't about to expire, a new inspection is not required at sale. The buyer files a Notice of Change in Ownership within 30 days of closing, with the fee, so the permit moves into their name.
How the point-of-sale inspection works
A City-Registered OWTS Inspector evaluates the system and files an inspection report with the city. A typical inspection looks at the tank, the disposal field or seepage pit, the distribution system and the condition of any advanced treatment components. The inspector may pump the tank and run water through the system to test how it performs.
If the system passes, the city issues the operating permit. Permits renew on a cycle that depends on the type of system, so ask when the next renewal is due.
What happens if the system fails
A failed inspection does not automatically kill a sale. Under the city's procedure:
The owner signs and notarizes a compliance agreement within 30 days of the failure date.
The city issues a certificate of inspection within 45 days of the failure date, which lets the transaction proceed.
The required repairs, upgrades or replacement must then be completed under the agreement before the operating permit is issued.
The practical question is who pays and when. Buyers and sellers can negotiate a credit, a price change, a holdback in escrow, or a repair before closing. A replacement system, especially one requiring advanced treatment, can be a major cost and may need its own permits.
Fire-destroyed homes and septic
Malibu has special procedures when the house has burned. The city's change-in-ownership form says that when the house was destroyed by fire, the new owner must act within 30 days of the sale: either abandon the system under a Building Safety permit, or enter a compliance agreement with the city and have the existing system inspected so it can serve the rebuilt home. For homes rebuilt after the Woolsey Fire, city policy has required the operating permit within 60 days of the Certificate of Occupancy. Ask the city which procedure applies to your property and fire.
The Civic Center exception
Properties in the Civic Center prohibition area, including the Malibu Colony, are being moved from septic systems to a central treatment plant in phases. If you are buying there, ask about the connection schedule and cost as well as the septic inspection.
Advice for sellers
Pull your OWTS permit history before you list. Check the expiration date.
If your permit is expired or close to it, order the inspection early, before you are in escrow.
If the system fails, get bids right away so buyers see a known cost, not an unknown risk.
Advice for buyers
Ask for the current operating permit, the latest inspection report and the pumping records.
Have your own inspector review the system and its capacity for any remodel you plan. More bedrooms can mean a bigger system.
Calendar the 30-day change-of-ownership filing for after closing.
Frequently asked questions
Is a septic inspection required to sell a house in Malibu?
Only if the home lacks a valid, unexpired operating permit. If a valid permit exists, the buyer files a change-of-ownership notice within 30 days of closing.
Who can inspect a septic system in Malibu?
A City-Registered OWTS Inspector. The city maintains the registry.
Can I sell a Malibu home with a failed septic system?
Yes. The owner signs a notarized compliance agreement within 30 days, and the city issues a certificate of inspection within 45 days so the sale can proceed. The repairs still have to be done.
Does a remodel trigger septic upgrades?
It can. Adding bedrooms or modifying the system can require an upgrade. Check with the city's Environmental Health staff early in design.
Plan the septic step first
Septic issues are easiest to solve before a listing goes live. If you are buying, start with my Malibu neighborhoods guide and beachfront buyer's guide. Questions about a specific property? Call or text 310.480.0288, email alex@flynnla.com, or contact me here.